Thinking of adding more space to your London home? A Loft Conversion London is one of the most practical ways to increase your property’s value and create much-needed room—without having to move. But one of the most common questions homeowners ask is, “How long does a loft conversion take?” The answer depends on the type of conversion, the structure of your existing home, and the complexity of the design. Whether you’re considering a simple rooflight loft or a full-scale dormer extension, understanding the timeline helps set realistic expectations and prepare for every phase of the process.

Here, we break down the typical stages of a loft conversion and provide a detailed look at how long each part takes, helping you plan your project more efficiently.

Initial Consultation and Design – 1 to 3 Weeks

Every loft conversion starts with a consultation, survey, and architectural design. During this phase, the team will visit your home, inspect the roof space, and discuss your ideas and requirements. This stage usually takes one to three weeks, depending on how quickly decisions are made and how complex the design is.

Your chosen architect or loft specialist will create initial sketches and floorplans, making adjustments based on your feedback. Once you approve the layout, the technical drawings needed for planning and construction can be prepared.

Planning Permission and Approvals – 2 to 8 Weeks

Depending on your location and the scope of the conversion, planning permission may or may not be required. Most loft conversions fall under permitted development rights, but more complex builds or homes in conservation areas may require formal permission.

Expect two to eight weeks for this stage, including time for Party Wall Agreements if necessary. Partnering with an experienced Loft Company London helps ensure your paperwork and approvals are managed efficiently.

Pre-Build Preparations – 1 to 2 Weeks

Once planning is sorted, your builder will begin preparing the site. This involves organising scaffolding, ordering materials, and finalising the project timeline. This usually takes one to two weeks, and while there’s not much physical construction at this stage, it’s a vital part of staying on schedule.

Construction Phase – 4 to 8 Weeks

The bulk of your loft conversion happens during the construction stage. On average, this takes four to eight weeks, depending on the type of conversion:

  • Rooflight conversions (least invasive): 4–5 weeks

  • Dormer conversions (most common): 6–8 weeks

  • Hip-to-gable or mansard conversions (more complex): 7–10 weeks

During this phase, your loft structure is reinforced, the new floor is built, insulation and windows are installed, and dormers or roof changes are completed if required.

Internal Work and Finishing – 2 to 3 Weeks

Once the shell is built, internal work begins. This includes electricals, plastering, flooring, painting, and fitting staircases or en-suites. These finishing touches usually take two to three weeks, and although this phase is less noisy, it still requires access to your home and coordination between different trades.

If you’ve opted for a more detailed project like a Loft Conversion Chelmsford, customisation and bespoke fittings might take a bit longer to complete depending on your selections.

Snagging and Final Inspection – 1 Week

After the main work is done, the final phase involves checking for minor issues—commonly known as “snagging.” Expect up to one week for a final inspection, touch-ups, and handover. At this point, building control officers may also visit to certify the work complies with UK building regulations.

Homeowners in areas such as Loft Conversion Chiswick find that working with local professionals familiar with borough-specific regulations helps streamline this final step.

Total Timeframe: Around 8 to 12 Weeks

In total, a typical loft conversion project from start to finish takes between 8 to 12 weeks, assuming there are no major delays. While weather, material availability, or changes in scope can occasionally add time, working with a reputable and organised team keeps things moving smoothly.

So, whether you’re expanding for a growing family, adding a home office, or simply making the most of your property investment, understanding the loft conversion timeline is the first step toward success.

Let Neo Lofts help you unlock your home’s hidden potential—on time and on budget.